This page is an unofficial LFoD record and is not legal advice. Verify the document against the official source before relying on it.
SB243: relative to complete streets policies, establishing a complete streets pilot program, and making an appropriation therefor.
Bill details
Version history, amendments, and roll-call votes were not present in the imported local bill data.
Sponsors
- Dan Feltes Senate · Dist 15
- Regina Birdsell Senate · Dist 19
- Patricia Higgins House · Graf 12
Topics
Official links
SB 243-FN-A - AS AMENDED BY THE SENATE
02/23/2017 0470s
2017 SESSION
17-0964
06/01
SENATE BILL 243-FN-A
AN ACT relative to complete streets policies, establishing a complete streets pilot program, and making an appropriation therefor.
ANALYSIS
This bill requires the commissioner of the department of transportation to assist municipalities to implement complete streets projects.
This bill also establishes a pilot program in the department of transportation for facilitating matching grants to municipalities for complete streets projects and makes an appropriation for the pilot program.
- - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Explanation: Matter added to current law appears in bold italics.
Matter removed from current law appears [in brackets and struckthrough.]
Matter which is either (a) all new or (b) repealed and reenacted appears in regular type.
02/23/2017 0470s 17-0964
06/01
STATE OF NEW HAMPSHIRE
In the Year of Our Lord Two Thousand Seventeen
AN ACT relative to complete streets policies, establishing a complete streets pilot program, and making an appropriation therefor.
Be it Enacted by the Senate and House of Representatives in General Court convened:
1 New Paragraph; Department of Transportation; Duties of Commissioner; Complete Streets. Amend RSA 21-L:4 by inserting after paragraph VI the following new paragraph:
VII. Prioritize applications by municipalities for the implementation of complete streets programs.
2 New Subdivision; Complete Streets. Amend RSA 228 by inserting after section 115 the following new subdivision:
Complete Streets
228:116 Definition; Complete Streets. "Complete streets" are those that provide safe and accessible options for walking, biking, transit, and vehicles for people of all ages and abilities.
228:117 Complete Streets Matching Grants Pilot Program.
I. The commissioner shall:
(a) Formalize criteria for municipal project applications for complete streets projects including a requirement of at least 60 percent municipal or private leveraging.
(b) Create a guidebook for establishing a transit system and encouraging walking and biking as viable means of transportation.
(c) Update the state's minimum geometric guidelines for local roads and streets, as well as any other out-of-date documents.
II. There is hereby established a matching grants pilot program to facilitate grants to municipalities for complete streets programs. The commissioner's implementation of this pilot program shall be consistent with paragraph I and grant applicants and recipients shall not be subject to the requirements of the United States Department of Transportation's Transportation Alternatives Program. The commissioner shall prioritize grant applications with higher municipal shares or private leveraging and grant applications most consistent with criteria and policies developed under paragraph I.
III. The commissioner shall report on the pilot program established in paragraph II on or before November 1, 2018, to the speaker of the house of representatives, the president of the senate, and the governor. The report shall include the number and types of grant applications received and funded, the estimated return on investment from the grants, and any other relevant information necessary to evaluate the effectiveness of the pilot program.
3 Department of Transportation; Appropriation. The sum of $2,500,000 for the fiscal year ending June 30, 2018 is hereby appropriated to the department of transportation for the purposes of the complete streets pilot program under RSA 228:117. This appropriation is in addition to any other funds appropriated to the department. The governor is authorized to draw a warrant for said sums out of any money in the treasury not otherwise appropriated.
4 Repeal. The following are repealed:
I. RSA 228:117, relative to complete streets matching grants pilot program.
II. RSA 228:116, relative to a definition of "complete streets."
5 Effective Date.
I. Section 4 of this act shall take effect November 1, 2018.
II. The remainder of this act shall take effect July 1, 2017.
LBAO 17-0964
Amended 2/24/17
SB 243-FN-A- FISCAL NOTE
AS AMENDED BY THE SENATE (AMENDMENT #2017-0470s)
AN ACT relative to complete streets policies, establishing a complete streets pilot program, and making an appropriation therefor.
FISCAL IMPACT: [ X ] State [ ] County [ X ] Local [ ] None
Estimated Increase / (Decrease)
STATE:
FY 2018
FY 2019
FY 2020
FY 2021
Appropriation
$2,500,000
$2,500,000
$0
$0
Revenue
$0
$0
$0
$0
Expenditures
Indeterminable Increase
Indeterminable Increase
$0
$0
Funding Source:
[ X ] General [ ] Education [ ] Highway [ ] Other
LOCAL:
Revenue
Indeterminable Increase
Indeterminable Increase
$0
$0
Expenditures
Indeterminable Increase
Indeterminable Increase
$0
$0
METHODOLOGY:
This bill establishes a two-year complete streets matching grants pilot program to provide safe and accessible options for walking, biking, transit, and vehicles for people of all ages and abilities. This bill also appropriates $2,500,000 in each FY 2018 and FY 2019 to the Department of Transportation for these purposes.
The Department of Transportation states development and oversight of the program would require additional staff time and resources. The Department assumes all staff time would be attributed to Civil Engineer VI Step 7 positions at $67.83 per hour and be paid for from the appropriation. Based on these assumptions the Department estimates the following program expenditures in FY 2018:
Expenditure
Staff Hours
Hourly Rate
Program Costs
Develop Complete Streets Program and Criteria
320
$67.83
$21,705
Create Guidebook
560
$67.83
$37,985
Update Highway Design Manual
160
$67.83
$10,853
Program Management and Oversight
500
$67.83
$33,915
Total
1540
$67.83
$104,458
The Department estimates a 1.5 percent increase in program management and oversight expenditures in FY 2019 for a total of $34,424 toward program costs in this fiscal year. There would be indeterminable state and local expenditures and local revenues to the extent localities participate in the pilot program each fiscal year. The Department notes the bill does not specify minimum match requirements for the program.
AGENCIES CONTACTED:
Department of Transportation