RSA 162-H:16 · Findings and Certificate Issuance

162-H:16 Findings and Certificate Issuance. –

Copy link
I.

The committee shall incorporate in any certificate such terms and conditions in their entirety and without addition, deletion, or change, as may be specified to the committee by any of the state agencies having permitting or other regulatory authority, under state or federal law, to regulate any aspect of the construction or operation of the proposed facility; provided, however, the committee shall not issue any certificate under this chapter if any of the state agencies denies authorization for the proposed activity over which it has permitting or other regulatory authority. The denial of any such authorization shall be based on the record and explained in reasonable detail by the denying agency.

Copy link
II.

Any certificate issued by the site evaluation committee shall be based on the record. The decision to issue a certificate in its final form or to deny an application once it has been accepted shall be made by a majority of the full membership. A certificate shall be conclusive on all questions of siting, land and offshore uses, and air and water quality.

Copy link
III.

The committee may consult with interested regional agencies and agencies of border states in the consideration of certificates.

Copy link
IV.

After due consideration of all relevant information regarding the potential siting, or routes of a proposed energy facility, including potential significant impacts and benefits, the site evaluation committee shall determine if issuance of a certificate will serve the objectives of this chapter. In order to issue a certificate, the committee shall find that:

Copy link
(a)

The applicant has adequate financial, technical, and managerial capability to assure construction and operation of the facility in continuing compliance with the terms and conditions of the certificate.

Copy link
(b)

The site and facility will not unduly interfere with the orderly development of the region with due consideration having been given to the views of municipal and regional planning commissions and municipal governing bodies.

Copy link
(c)

The site and facility will not have an unreasonable adverse effect on aesthetics, historic sites, air and water quality, the natural environment, fish and wildlife resources, public health and safety, and existing land and offshore uses.

Copy link
(d)

[Repealed.]

Copy link
(e)

Issuance of a certificate will serve the public interest.

Copy link
V.

The committee shall issue an order granting or denying a certificate. Such order shall summarize issues of concern expressed during public information sessions and hearings to ensure that the public's voice has been heard and recorded.

Copy link
VI.

A certificate of site and facility may contain such reasonable terms and conditions, including, but not limited to the authority to require bonding, as the committee deems necessary. Such certificates, when issued, shall be final and subject only to judicial review.

Copy link
VII.

The committee may condition the certificate upon the results of applicable federal approvals or appeal processes and required federal and state agency studies whose study period exceeds the application period. Source. 1991, 295:1. 2009, 65:18-21, 24, IX, eff. Aug. 8, 2009. 2014, 217:20-22, eff. July 1, 2014. 2015, 264:2, eff. July 20, 2015. 2023, 233:14, eff. Oct. 7, 2023. 2024, 212:9, 10, eff. July 19, 2024.

Copy link

Source note

Source. 1991, 295:1. 2009, 65:18-21, 24, IX, eff. Aug. 8, 2009. 2014, 217:20-22, eff. July 1, 2014. 2015, 264:2, eff. July 20, 2015. 2023, 233:14, eff. Oct. 7, 2023. 2024, 212:9, 10, eff. July 19, 2024.

Source history

  • 1991, 295:1
  • 2009, 65:18-21, 24, IX, eff. Aug. 8, 2009
  • 2014, 217:20-22, eff. July 1, 2014
  • 2015, 264:2, eff. July 20, 2015
  • 2023, 233:14, eff. Oct. 7, 2023
  • 2024, 212:9, 10, eff. July 19, 2024

Related materials

Bill relationships

  • 2026 HB707-FN reference

    the date on which the application is first submitted to the committee. IX. "Human health" is defined to be consistent with "public health and safety" as that term is utilized in RSA 162-H. X. "Landfill expansion" means an addition to the permitted capacity of an existing facility as defined in RSA 149-M:4, IX. XI. “Major solid waste disposal facility” means a location, system, or physical structure f

  • 2026 SB518 amend

    de the department and consumer advocate with such confidential information. 5 New Section; Application for Certificate; Qualified Transmission Asset Replacement Projects. Amend RSA 162-H by inserting after section 7-b the following new section: 162-H:7-c. Application for Certificate; Qualified Transmission Asset Replacement Projects. I. This section applies only to certification of qualified trans

  • 2026 SB518 amend

    avel and related expenses associated with the processing of an application or other proceedings under this chapter. 8 New Subparagraph; Findings and Certificate Issuance. Amend RSA 162-H:16, IV by inserting after subparagraph (e) the following new subparagraph: (f) In determining whether the issuance of a certificate for a transmission asset replacement project that is not qualified serves the public i