RSA 374:41 · Commission May Institute

374:41 Commission May Institute. – Whenever the commission shall be of opinion that a public utility is failing or omitting, or about to fail or omit, to do anything required of it by law or by order of the commission, or is doing anything, or about to do anything, or permitting anything, or about to permit anything, to be done contrary to, or in violation of, law or any order of the commission, it shall have authority to lay the facts before the attorney general, and to direct him immediately to begin an action in the name of the state praying for appropriate relief by mandamus, injunction or otherwise. Source. 1911, 164:16. PL 240:39. RL 289:39. 1951, 203:44, eff. Sept. 1, 1951.

Copy link

Source note

Source. 1911, 164:16. PL 240:39. RL 289:39. 1951, 203:44, eff. Sept. 1, 1951.

Source history

  • 1911, 164:16. PL 240:39. RL 289:39
  • 1951, 203:44, eff. Sept. 1, 1951

Related materials

Bill relationships

  • 2026 HB1743 amend

    mart meters. Be it Enacted by the Senate and House of Representatives in General Court convened: 1 New Section; Public Utilities; Smart Meter Radiation Disclosure. Amend RSA 374 by inserting after section 2-a the following new section: 374:2-b Smart Meter Radiation Disclosure. I. Each electric utility operating in the state shall provide an annual written statement to each utility account h

  • 2026 HB1743-FN amend

    mart meters. Be it Enacted by the Senate and House of Representatives in General Court convened: 1 New Section; Public Utilities; Smart Meter Radiation Disclosure. Amend RSA 374 by inserting after section 2-a the following new section: 374:2-b Smart Meter Radiation Disclosure. I. Each electric utility operating in the state shall provide an annual written statement to each utility account h

  • 2026 HB1745 amend · effective 2027-01-01

    ity costs to ratepayers. Be it Enacted by the Senate and House of Representatives in General Court convened: 1 New Section; Prohibited Cost Recovery Through Rates. Amend RSA 374 by inserting after section 2-a the following new section: 374:2-b Prohibited Cost Recovery Through Rates. I. No public utility shall recover through rates any costs associated with its attendance at, participation i

  • 2026 HB1745-FN amend · effective 2027-01-01

    ity costs to ratepayers. Be it Enacted by the Senate and House of Representatives in General Court convened: 1 New Section; Prohibited Cost Recovery Through Rates. Amend RSA 374 by inserting after section 2-a the following new section: 374:2-b Prohibited Cost Recovery Through Rates. I. No public utility shall recover through rates any costs associated with its attendance at, participation i

  • 2026 SB540 amend · effective 2027-01-01

    Each plug-in solar generation system shall be installed and operated in accordance with the state building code and manufacturer instructions. 4 New Section; Liability. Amend RSA 374 by inserting after section 1-a the following new section: 374:1-b Liability for Plug-In Solar Generation Systems. An electric distribution utility shall not be liable for damage, injury, or compensation or charges ari

  • 2026 SB540-FN amend · effective 2027-01-01

    Each plug-in solar generation system shall be installed and operated in accordance with the state building code and manufacturer instructions. 4 New Section; Liability. Amend RSA 374 by inserting after section 1-a the following new section: 374:1-b Liability for Plug-In Solar Generation Systems. An electric distribution utility shall not be liable for damage, injury, or compensation or charges ari