RSA 486-A:8 · Priority of Applications

486-A:8 Priority of Applications. –

Copy link
I.

For surface water treatment projects, the department shall establish and maintain a priority list of projects eligible to receive grants under RSA 486-A:3. The priority list shall include the highest priority projects ready for construction and anticipated to receive grants from appropriated funds within the next fiscal year. The list required by this section shall not be considered rules subject to the provisions of RSA 541-A.

Copy link
II.

For water supply land protection projects, the department shall prioritize projects in accordance with rules established under RSA 486-A:11. Prioritization factors shall include, but not be limited to:

Copy link
(a)

Distance from and relation to the drinking water source.

Copy link
(b)

Size of the area proposed for protection relative to the size of the source water protection area.

Copy link
(c)

Natural resource values, including wetlands, habitat protection, and recreational uses.

Copy link
(d)

Current protection status of the source water protection area.

Copy link
(e)

Ability of the applicant to pay for water supply land protection.

Copy link
III.

For regional water system projects and evaluation of groundwaters contributing area of public wells with recorded levels of chemical contaminants, the department shall adopt prioritization factors by rule under RSA 541-A, to assist in determining which new projects to fund under this chapter. Prioritization factors shall include, but not be limited to:

Copy link
(a)

The population of the service area that would receive water through the regional water system interconnection.

Copy link
(b)

The degree to which the public's health, safety, and economic well-being will benefit.

Copy link
(c)

The fiscal impact on user fees and taxes in the area of the regional water system.

Copy link
(d)

The consistency with land use master plans in the affected municipalities and with the provisions of RSA 9-B and RSA 162-C:2, V, to the extent that a proposed regional water system project may impact the municipality's growth and development patterns. Source. 1993, 341:1. 2000, 310:1. 2003, 178:10, eff. July 1, 2003.

Copy link

Source note

Source. 1993, 341:1. 2000, 310:1. 2003, 178:10, eff. July 1, 2003.

Source history

  • 1993, 341:1
  • 2000, 310:1
  • 2003, 178:10, eff. July 1, 2003