RSA 676:11 · Building Permits Required
676:11 Building Permits Required. – After a municipality has adopted a building code, any person who intends to erect or remodel any building in the municipality shall submit the plans to the building inspector for the building inspector's examination and approval prior to commencement of the planned construction. Source. 1983, 447:1. 1996, 226:2, eff. Jan. 1, 1997.
Copy linkSource note
Source. 1983, 447:1. 1996, 226:2, eff. Jan. 1, 1997.
Source history
- 1983, 447:1
- 1996, 226:2, eff. Jan. 1, 1997
Related materials
Bill relationships
-
2026 HB244
related · effective 2026-07-01
ition of zoning ordinance or building code. IV. RSA 674:34, relative to powers of building code board of appeals. V. RSA 674:52-a, relative to ordering building vacated. VI. RSA 676:11, relative to building permits required. VII. RSA 676:13, relative to building permit restrictions. 64 Effective Date. This act shall take effect at 12:01 a.m. on July 1, 2026. HELPFUL LINKS Redistricting Informat
-
2026 SB508
amend
hwith transmit to the board all the papers constituting the record upon which the action appealed from was taken. 2 New Section; Stamping and Acceptance of Revised Plans. Amend RSA 676 by inserting after section 5 the following new section: 676:5-a Stamping and Acceptance of Revised Plans. I. Each city, town, or municipality shall stamp and accept revised plans submitted by an applicant within 10 b