RSA 240:3 · Implementation of Plan

240:3 Implementation of Plan. –

Copy link
I.

The department of transportation shall be responsive to requests for information relative to the plan.

Copy link
II.

The plan shall include a list of projects intended to be under construction in the next 10 years with dates and costs of construction.

Copy link
III.

Preliminary studies, design, and right of way funding for long term projects that have been approved by the Governor's Advisory Commission on Intermodal Transportation (GACIT) and the department of transportation shall be included in the plan.

Copy link
IV.

The governor shall transmit the plan to the general court by January 15 of each even-numbered year. Projects listed in the plan shall be listed by the year the funds are to be expended and the 10 years of the plan shall be financially constrained.

Copy link
V.

Projects listed in the plan, except projects which are solely for infrastructure preservation or which stem from statewide transportation programs included in the plan, shall be prioritized based on a department of transportation methodology that examines the certainty of a project relative to its scope, cost, constructability, permitability, and public support, provided that the project has the following:

Copy link
(a)

Preliminary design.

Copy link
(b)

Environmental evaluation.

Copy link
(c)

A public participation process.

Copy link
(d)

Available and adequate funding.

Copy link
VI.

The following shall be considered for any project proposed for the plan:

Copy link
(a)

Safety.

Copy link
(b)

Multimodalism.

Copy link
(c)

Land use.

Copy link
(d)

Infrastructure preservation.

Copy link
(e)

Overall corridor improvement.

Copy link
(f)

For any project located in the coastal and Great Bay regions of the state, the project shall reference as guidance for all potentially affected activities in said regions the requirements regarding coastal resilience and economic development in RSA 483-B:22.

Copy link
VII.

Every 2 years, the department of transportation shall propose to the general court a list of projects to be removed from the 10-year plan if the department determines that any project:

Copy link
(a)

Has significantly changed in scope; or

Copy link
(b)

Is no longer financially or environmentally feasible; or

Copy link
(c)

Lacks the necessary permits; or

Copy link
(d)

For other reasons is unnecessary or unlikely to proceed.

Copy link
VIII.

Inflation shall be included in the costs calculated in the 10-year plan and shall also be included in calculating the necessary revenues.

Copy link
IX.

The department of transportation shall meet at least semi-annually with the GACIT.

Copy link
X.

The GACIT shall review:

Copy link
(a)

Department of transportation financial status and issues.

Copy link
(b)

The status and issues of transportation projects.

Copy link
(c)

Other ongoing initiatives and issues.

Copy link
XI.

The GACIT shall provide the first statewide review of the plan as drafted by the department of transportation with input from the regional planning commissions. Source. 2010, 2:1, eff. April 2, 2010; 231:10, 11, eff. June 28, 2010. 2019, 318:7, eff. Oct. 2, 2019.

Copy link

Source note

Source. 2010, 2:1, eff. April 2, 2010; 231:10, 11, eff. June 28, 2010. 2019, 318:7, eff. Oct. 2, 2019.

Source history

  • 2010, 2:1, eff. April 2, 2010; 231:10, 11, eff. June 28, 2010
  • 2019, 318:7, eff. Oct. 2, 2019

Related materials

Bill relationships

  • 2026 HB2026 add · effective 2026-12-01

    by adopts the plan known as the “State of New Hampshire Ten Year Transportation Improvement Plan 2027-2036" submitted by the governor to the legislature pursuant to RSA 228:99 and RSA 240, with the following revisions, and encourages expeditious implementation of the projects shown therein. 2 Albany; Project Added. The project named Albany project number 45469, operational and safety improvements at

  • 2025 HB2 reference

    114 State and Federal Funding. I. Any public-private partnership projects utilizing federal or state funding shall be approved as part of the state 10-year transportation improvement program in accordance with RSA 240. II. All proceeds or revenues to the state derived from public-private partnerships and intended for payment to the department of transportation shall be credited to the department of transportation, restricte