This page is an unofficial LFoD record and is not legal advice. Verify the document against the official source before relying on it.

Eastman v. Newman and Trustees; Batchelder v. Same; Moore Et Al. v. Same; Flint v. Same; Hall v. Same

June 1, 1880 - Opinion

Unanimous

Case records

Open case page
Date Record Text Type Party PDF
June 1, 1880 Eastman v. Newman and Trustees; Batchelder v. Same; Moore et al. v. Same; Flint v. Same; Hall v. Same Current page Opinion Supreme Court Reporter

Eastman v. Newman and Trustees. Batchelder v. Same. Moore & a. v. Same. Flint v. Same. Hall v. Same.

A sub-contractor, who performs labor or furnishes materials for erecting a building, but neglects to give notice in writing to the owner that he claims a lien therefor, acquires no lien upon the building for such labor or materials.

N. agreed with C. and Y. to erect for them a building for a fixed price. E., a creditor of N., attached certain lumber belonging to N. C. receipted for the lumber, and N. used it in the construction of the building. E., with other creditors of N., attached by trustee process the funds due from C. and Y. to N. P. had a lien on the building for materials used in its erection. Held, that in computing the amount for which C. and Y. were chargeable as trustees, the value of the lumber receipted for, and the amount which-they were compelled to pay P. to discharge his lien, should be deducted from the price due for the erection of the building.

Foreign Attachment. Facts found by the court. In August, 1879, Newman, by a parol contract, engaged to build for the trustees, Clough and Y oung, upon land owned by them, a dwelling-house, according to certain plans and specifications, furnishing all the labor and materials, for the sum of $1,600. The trustees were to own the house in equal shares. The understanding at first was that each of the trustees would pay $100 a week until the whole sum should be paid, and that the work would be completed in eight weeks from its commencement; but this understanding was not carried out, either as to the time within which the work was completed, or the manner in which the payments were made. Newman began work October 9, 1879, and the building was substantially completed January 9, 1880, at which time he had furnished extra work and materials of the value of $58.22. October 24, one Parker served a written notice bn Clough to the effect that he claimed a lien upon the building for materials furnished and to be furnished, by virtue of a written contract with Newman. January 8 the trustees paid Parker $94.51 in settlement of his claim, and prior to that date Clough paid Newman $75, to be used in paying Parker’s claim. Prior to January 2, Clough paid Newman $527.38, and Young paid him $697.25, including the sum of $94.51 paid in settlement of the Parker claim. Thus the total amount of payments to Newman, including the sum of $200 paid prior to October 23, was $1,424.63. Irrespective of the trustee process, there is due from the trustees §283.59.

The funds in the hands of the' trustees were attached in the following order: By Batcbelder, October 23; by Moore & Sons, October 23; by Eastman, January 2; by Flint, January 9; by Hall, January 9. Batcbelder and Moore & Sons attached a quantity of lumber of tbe value of §120, intended for use in tbe construction of tbe buildmg. Clough receipted for tbe lumber, and it was used for tbe purpose intended. Eastman furnished materials for tbe building, and attached it as tbe property of Newman, bis writ containing a precept to tbe officer to attach it to secure bis lien for materials furnished in its construction. Tbe claims of Flint and Hall were for labor done upon tbe building.

Tbe court held tbe trustees chargeable to Batcbelder and Moore & Sons, in tbe order of their attachments, for tbe amount of their respective claims, after deducting tbe sum of §120, tbe amount of tbe receipt to tbe attaching officer. Tbe court held that Eastman was not entitled to priority by force of any lien upon tbe buildings, and be excepted. Tbe court reserved tbe question whether tbe trustees are chargeable in tbe actions of Eastman, Flint, and Hall.

Shirley Carr, for Eastman.

Leach $ Stevens, for Batcbelder and Moore & Sons, and for tbe trustees in tbe other actions.

Flanders, for Flint and Hall.

Smith, J.

Neither of tbe plaintiffs having given notice in writing to tbe trustees that be should claim a lien for labor to be performed or materials to be furnished, has acquired any lien on tbe building. G. L., c. 139, s. 15. Tbe lien of tbe several plaintiffs on tbe funds in tbe bands of tbe trustees is determined by tbe priority of their respective attachments.

Tbe value of tbe lumber receipted for by Clough, and fixed in tbe receipt to the officer at §120, should be reckoned as paid by tbe trustees, and be deducted from tbe amount due to Newman, tbe lumber having been used in tbe construction of tbe bouse. Tbe contract is treated by all parties as tbe joint contract of Clough and Young; and that was evidently tbe understanding of tbe parties, although, as between Clough and Young, each was to pay one half of the-contract price to Newman. They are jointly and severally liable to him. It makes no difference that the receipt was signed by Clough alone. It was a liability incurred for tbe defendant Newman, against which they are entitled to secure themselves by withholding that amount from tbe funds in their bands, and which they are equitably entitled to set off against tbe price to be paid to Newman. They should also be credited with tbe sum of §91.51, paid in settlement of Parker’s claim. Parker had given the statute notice to Clough, and had acquired a valid lien at least upon Clough’s undivided interest in the building, which had priority over the claims of Eastman, Flint, and Hall. Each trustee being liable to Newman for the whole price of the building, the trustees, and each of them, were obliged to pay Parker’s claim to discharge his lien. No question is made as to the validity or amount of his claim.

If the sum of S75 was paid to Newman before service of the writs upon the trustees, it would be a payment to that extent for which the trustees should be credited. If paid after service upon the trustees, and Newman retained the money instead of paying it over to Parker, the payment cannot avail the trustees as against the plaintiffs. But if paid to Parker, whether paid before or after service on the trustees, the payment having been made to discharge a lien upon the property which had priority over the plaintiffs’ lien, the trustees are to be credited with the payment.

The trustees claim that Newman has not completed the building, and therefore is not entitled to receive the full contract price. This claim is in conflict with the reserved case; but if it were not, it would be a question to be determined at the trial term. Whether Batchelder and Moore & Sons have taken executions against the trustees for sums larger than they were entitled to (as claimed by Eastman), is also to be determined at the trial term.

Eastman also raises the question whether, having attached the building as the property of Newman, he may not hold it as Newman’s to the extent that it was not paid for? That question can only be met when the question of ownership is properly before the court. It would seem, however, that if the trustees are charged for the balance due for constructing the building, the question proposed could not arise, the building being fully paid for.

Whether the trustees are chargeable, and if so, for what sum, will be determined at the trial term upon the principles thus laid down.

Case discharged.

Foster, J., did not sit: the others concurred.